4.3.2 Inspection routine. The sample shall be subjected to the inspections specified in table IV and
table V. The leakage test, when applicable, shall follow the rough handling test.
4.3.3 Failures. One or more failures shall be cause for refusal to grant first article approval.
4.4.4 Resubmission of first article sample. If the sample fails to pass first article inspection, the
contractor shall change the preservation and packing processes to correct the cause of the deficiency.
First article inspection shall be performed on a corrected sample to prove that the corrective action is
acceptable.
4.4 Conformance inspection. This inspection shall consist of the inspections and tests specified in
table IV and table V.
4.4.1 Shipments to Government activities.
4.4.1.1 Inspection lot. An inspection lot, as far as practicable, shall consist of unit or exterior (shipping)
packs produced under essentially the same conditions and offered for inspection at one time. For the
purpose of selecting samples to be inspected and tested for compliance with the requirements of this
specification, either items in process or completed packs except as stated herein, may be combined into
lots without regard to individual items, contracts, or the quantities therein. Unit packs of the same size
and made from the same packaging materials may be grouped together except when item complexity,
item value, or the complexity of the preservation method warrants that the inspection of such items be
performed on a separate basis. A separate application of the sampling or inspection shall be made on
these items. The combination of items to be subjected to inspection shall be determined by either the
Government or the contractor, subject to the approval of the Government.
4.4.1.2 Visual and dimensional inspection. Visual and dimensional inspection shall consist of those
inspections specified in table IV.
TABLE IV. Visual and dimensional inspections.
Major defects
Requirement
Method
paragraph
paragraph
Preservation and packing materials not conforming
3.1.1, 3.1.2, 3.1.3,
to referenced specification requirements
and 3.2
Improper field force protection (shielding)
3.1.8 and 3.2
Punctured or improperly fabricated barrier bag
3.1.1.4 and 3.2
Uncleaned or improperly cleaned items
3.1.2.1.1 and 3.2
4.5.1
Incorrect preservation method
3.1.2.1.3 and 3.2
Wrong quantity per unit pack
3.1.2.1.4
Nonusable or incorrect kind or application of
3.1.2.1.7 and 3.2
intermediate containers
Improper box closures
3.1.3 and 3.2
Omitted, incorrect, or illegible marking
3.1.5 and 3.2
4.4.1.3 Sample plan. A sample of five packages shall be randomly selected. If one or more defects
are found, the inspection lot shall be screened and the defective packages removed. A new sample of
five packages shall be randomly selected. If any defects are found in the second sample, the inspection
lot shall be rejected and shall not be supplied to the resistor specification.
4.4.1.4 Disposition of sample units. Sample units which have passed all the inspection specified in
table IV may be delivered on the contract, provided the lot is accepted.